CDM 2015
Do I need a Principal Contractor?
Yes, if more than one contractor will work on your project. Here is how to tell.
Yes, if more than one contractor will work on your project. The size of the job does not change this. A two-week refit with a joiner and an electrician counts. (CDM 2015, regulation 5.)
Three questions
- Will more than one contractor work on the job, at any time? If yes, you must appoint a Principal Contractor and a Principal Designer, in writing.
- Has the construction phase started? The appointment must be made before it does, and as early as you can.
- Is the job notifiable? It is if it will last more than 30 working days with more than 20 workers on site at the same time, or exceed 500 person days. Then HSE must be told on an F10 before work starts, and the notice displayed on site.
What if I don't appoint one?
Then you carry the Principal Contractor's duties yourself: the plan, the welfare, the site security, the inductions and the coordination of every contractor (regulation 5(4)). HSE prosecutes clients and developers who leave these duties unmet.
I'm a homeowner
On a home project with more than one contractor, your duties pass to the Principal Contractor automatically (regulation 7). You still need one.
Is there a Principal Contractor licence?
No. There is no licence or register for Principal Contractors in the UK. What CDM 2015 asks for is competence: the Principal Contractor must have the skills, knowledge and experience for the job, and the organisational capability if it is a company, and you must take reasonable steps to check before you appoint (regulation 8). Ask for their site management qualifications, insurance and examples of similar work.
Where the rules come from
The Construction (Design and Management) Regulations 2015, and HSE's guide to them, L153. HSE explains the role on its Principal Contractor page.