Most building work in schools, offices, shops and clinics happens while the building is still in use. Staff, pupils, patients, customers and visitors carry on around the site, and none of them have had a site induction. Keeping them apart from the work is the core of the job.
Here's how we plan it.
Know who uses the building, and when
Start with the building's own people: how many, where they go, their hours, and who's vulnerable. Children, patients, elderly people and people with disabilities need more care. Find out about lesson changes, visiting hours, deliveries, events and exams, and plan the noisiest and riskiest work around them.
Segregation
- A clear boundary: solid hoarding or secure fencing between the work and the building's users, not tape or cones. Inside, full-height dust screens where the work sits next to occupied rooms.
- Separate routes: a contractors' entrance and route that doesn't cross public areas, wherever possible. Where routes must cross, control the crossing at agreed times.
- Locked when unattended: the work area secured at breaks and at the end of each day, with tools and materials put away.
Fire safety and escape routes
Building work changes the building's fire strategy: escape routes may be blocked, fire doors propped, alarms isolated and hot work carried out. Agree with the building's responsible person how escape routes, alarms and fire doors will be kept working, what temporary arrangements are needed, and how the site's own evacuation fits with the building's. Test it.
Noise, dust and vibration
Agree the quiet times and stick to them. Control dust at source with extraction and water, and seal off ventilation that could carry dust into occupied areas. Plan for the building's existing hazards too: older schools, offices and hospitals may contain asbestos, which must be surveyed before work disturbs it.
Deliveries and vehicles
Book deliveries outside the busiest times, such as the school run or clinic opening, with a banksman where vehicles must reverse or cross pedestrian routes. Keep the delivery area separate from parking and drop-off areas.
Communication
- One named contact for the building's management, and a regular short meeting.
- Advance notice to staff and users of noisy work, route changes and service shutdowns.
- Clear signs at every boundary and diversion.
- A way for building users to report concerns that reaches the site manager the same day.
Phasing
Larger projects in occupied buildings are often done in phases, moving people out of one area at a time. Each phase needs its own boundary, routes and fire arrangements, and a check before the building's users move back in.
Occupied and phased works are a large part of what we do; see who we work for. To talk about your building, email gs [at] gewell [dot] co [dot] uk.