Employing your own trades? How a separate Principal Contractor works

Plenty of clients don't use a main contractor. A retailer appoints its own shopfitter, electrician and flooring firm. A facilities team calls in its usual trades. A developer manages the packages itself. It can save money and keep control, but it doesn't remove the law: with more than one contractor on the job, someone must be appointed Principal Contractor, in writing, before work starts.

If you don't appoint one, you take on the duties yourself. Here's how a separate Principal Contractor appointment works instead.

Who does what

  • You, the client, keep your contracts with each trade: the price, the programme, the payment and the quality of their work.
  • The Principal Contractor plans, manages and coordinates health and safety during the construction phase: the construction phase plan, the site set-up and welfare, the inductions, site security, the coordination between trades, and keeping the plan up to date.
  • Each trade plans and manages its own work safely, and must follow the Principal Contractor's directions and the construction phase plan.

This works well when it's agreed clearly at the start. It goes wrong when nobody tells the trades.

Put it in the trade contracts

Tell every trade, in their contract or order, that a Principal Contractor has been appointed, and that they must:

  • provide their method statements and evidence of competence before starting;
  • attend the site induction and sign in every day;
  • follow the construction phase plan, the site rules and the Principal Contractor's directions;
  • apply for permits for high-risk work;
  • report accidents, incidents and near misses;
  • provide the information needed for the health and safety file.

Without this, a trade can fairly say they didn't know.

Give the Principal Contractor what they need

The Principal Contractor can only plan what they know about. Share the pre-construction information early: the building, its hazards and any asbestos survey, the existing services, the occupants and their hours, and the list of trades with their dates. Tell them when a new trade is added or the programme changes.

Control of the site

The trades are yours, but the site must be under the Principal Contractor's control while the work goes on. That means one gate, one sign-in, one induction and one set of site rules for everyone, including your own staff and visitors who come into the work area. Agree at the start how changes to the trades' work will be passed on, so the plan stays current.

Where we fit

Being Principal Contractor while you keep your own trades is one of the services we provide. We take the duties and control of the site; you keep your contracts. See our services and how we work, or email gs [at] gewell [dot] co [dot] uk.